Chapter 6 and 7 ProblemsPlease complete the following 8 exercises below in a word document (but must be single document). You must show your work where appropriate (leaving the calculations within Excel cells is acceptable).Chapter 6 Exercise 22. Schedule of cash collectionsSugarland Company sells a single product and anticipates opening a new facility in Charlotte on May 1 of the current year. Expected sale

Chapter 6 and 7 Problems

 

Please complete the following 8 exercises below in a word document (but must be single document). You must show your work where appropriate (leaving the calculations within Excel cells is acceptable).

Chapter 6 Exercise 2

2. Schedule of cash collections
Sugarland Company sells a single product and anticipates opening a new facility in Charlotte on May 1 of the current year. Expected sales during the first three months of activity are: May, $60,000; June, $80,000; and July, $85,000. Thirty percent of all sales are for cash; the remaining 70% are on account. Credit sales have the following collection pattern:
Collected in the month of sale 60%

Collected in the month following sale 35

Uncollectible 5

 

a. Prepare a schedule of cash collections for May through July.

b. Compute the expected balance in Accounts Receivable as of July 31.
Chapter 6 Exercise 4
4. Production and cash-outlay computations

RPR, Inc., anticipates that 120,000 units of product K will be sold during May. Each unit of product K requires four units of raw material A. Actual inventories as of May 1 and budgeted inventories as of May 31 follow.

 

  1-May 31-May
Product K (Units) 55,000 60,000
Rate Materials A (Units) 40,000 37,000

 

Each unit of raw material A costs $8; RPR pays for all purchases in the month of acquisition. Invoices that account for 80% of the cost of materials acquired will be paid within 10 days of receipt, entitling the company to a 2% cash discount.

 

a. Determine the number of units of product K to be manufactured in May.

b. Compute the May cash outlay for purchases of raw material A.

 

 

 

 

 

 

  July August September
Beginning cash balance $10,000 $ ? $ ?
Add: Cash receipts 50,000 63,000 71,000
Deduct: Cash payments -64,000 -58,000 -64,000
Cash excess (deficiency) before financing ($4,000) $ ? $ ?
Financing      
Borrowing to maintain minimum balance ? ? ?
Principal repayment ? ? ?
Interest payment ? ? ?
Ending cash balance $ ? $ ? $ ?

Chapter 6 Exercise 5
5. Abbreviated cash budget; financing emphasis

An abbreviated cash budget for Big Chuck Enterprises follows.
 

 

 

 

 

 

 

 

 

Big Chuck wishes to maintain a $10,000 minimum cash balance at all times. Additional financing is available (and retired) in $1,000 multiples at a 12% interest rate. Assume that borrowings take place at the beginning of the month; retirements, in contrast, occur at the end of the month. Interest is paid at the time of repaying principal and computed on the portion of principal repaid.

 

a. Find the unknowns in Big Chuck's abbreviated cash budget.

b. Determine the outstanding loan balance as of September 30, after any repayments have been made.
Chapter 6 Problem 3
3. Comprehensive budgeting

The balance sheet of Watson Company as of December 31, 20X1, follows.

WATSON COMPANY
Balance Sheet
December 31, 12X1
Assets    
Cash   $4,595
Accounts receivable   10,000
Finished goods (575 units x $7.00)   4,025
Direct materials (2,760 units x $0.50)   1,380
Plant & equipment $50,000  
Less: Accumulated depreciation 10,000 40,000
Total assets   $60,000
Liabilities & Stockholders' Equity    
Accounts payable to suppliers   $14,000
Common stock $25,000  
Retained earnings 21,000 46,000
Total liabilities &. stockholders' equity   $60,000

 

The following information has been extracted from the firm's accounting records:

1. All sales are made on account at $20 per unit. Sixty percent of the sales are collected in the month of sale; the remaining 40% are collected in the following month. Forecasted sales for the first five months of 20X2 are: January, 1,500 units,- February, 1,600 units; March, 1,800 units; April, 2,000 units; May, 2,100 units.

2. Management wants to maintain the finished goods inventory at 30% of the following month's sales.

3. Watson uses four units of direct material in each finished unit. The direct material price has been stable and is expected to remain so over the next six months. Management wants to maintain the ending direct materials inventory at 60% of the following month's production needs.

4. Seventy percent of all purchases are paid in the month of purchase; the remaining 30% are paid in the subsequent month.

5. Watson's product requires 30 minutes of direct labor time. Each hour of direct labor costs $7.

Instructions:

a. Rounding computations to the nearest dollar, prepare the following for January through March:

1) Sales budget

2) Schedule of cash collections

3) Production budget

4) Direct material purchases budget

5) Schedule of cash disbursements for material purchases
6) Direct labor budget

b. Determine the balances in the following accounts as of March 31:

1) Accounts Receivable

2) Direct Materials

3) Accounts Payable

 

Chapter 7 Exercise 3

3. Variances for direct materials and direct labor

Banner Company manufactures flags of various countries. Each flag has a standard of eight square feet of fabric and three hours of direct labor time. Information about recent production activity follows.

 

 

Actual cost of fabric: $4.50 per square foot

Fabric consumed: 32,080 square feet

Standard price per square foot of fabric: $4.25

Standard direct labor rate: $10.00 per hour

Actual direct labor rate: $10.20 per hour

Actual labor hours worked: 11,940

Actual production completed: 4,000 flags

 

a. Compute the materials price variance and the materials quantity variance.

b. Compute the labor rate variance and the labor efficiency variance.

 

Chapter 7 Exercise 5

5. Overhead variances

Nova Manufacturing applies factory overhead to products on the basis of direct labor hours. At the beginning of the current year, the company's accountant made the following estimates for the forthcoming period:

· Estimated variable overhead: $500,000

· Estimated fixed overhead: $400,000

· Estimated direct labor hours: 40,000

 

It is now 12 months later. Actual total overhead incurred in the manufacture of 7,900 units amounted to $895,100. Actual labor hours totaled 39,800. Assuming a direct labor standard of five hours per finished unit, calculate the following:

a. Variable overhead efficiency variance

b. Fixed overhead volume variance

c. Overhead spending variance
Chapter 7 Problem 1

1. P26-A1 Basic flexible budgeting (L.O. 2) 
Centron, Inc., has the following budgeted production costs:

Direct materials $0.40 per unit
Direct labor 1.80 per unit
Variable factory overhead 2.20 per unit
Fixed factory overhead
Supervision $24,000
Maintenance 18,000
Other 12,000

 

The company normally manufactures between 20,000 and 25,000 units each quarter. Should output exceed 25,000 units, maintenance and other fixed costs are expected to increase by $6,000 and $4,500, respectively.

During the recent quarter ended March 31, Centron produced 25,500 units and incurred the following costs:

 

Direct Materials   $10,710  
Direct Labor   47,175  
Variable factory overhead 51,940  
Fixed factory overhead      
Supervision   24,500  
Maintenance   23,700  
Other   16,800  
Total production costs   $174,825  

 

 

 

 

 

 

 

 

Instructions:

a. Prepare a flexible budget for 20,000, 22,500, and 25,000 units of activity.

b. Was Centron's experience in the quarter cited better or worse than anticipated? Prepare an appropriate performance report and explain your answer.

c. Explain the benefit of using flexible budgets (as opposed to static budgets) in the measurement of performance.

 

Chapter 7 Problem 5

5. P26-B3 Straightforward variance analysis (L.O. 5)

Arrow Enterprises uses a standard costing system. The standard cost sheet for product no. 549 follows.

Direct materials: 4 units @ $6.50   $26.00
Direct labor: 8 hours @ $8.50   68
Variable factory overhead: 8 hours @ $7.00 56
Fixed factory overhead: 8 hours @ 2.5 20
Total standard cost per unit   $170.00

 

The following information pertains to activity for December:

1. Direct materials acquired during the month amounted to 26,350 units at $6.40 per unit. All materials were consumed in operations.

2. Arrow incurred an average wage rate of $8.75 for 51,400 hours of activity.

3. Total overhead incurred amounted to $508,400. Budgeted fixed overhead totals $1.8 million and is spread evenly throughout the year.

4. Actual production amounted to 6,500 completed units.

 

Instructions:

a. Compute Arrow's direct material variances.

b. Compute Arrow's direct labor variances.

c. Compute Arrow's variances for factory overhead.

 

TutorPro
Calculate your paper price
Pages (550 words)
Approximate price: -
Tutorpro

High Quality Papers

We always make sure that writers follow all your instructions precisely. You can choose your academic level or professional level, and we will assign a writer who has a respective degree.

Tutorpro

Experienced Writers

We have a team of professional writers with experience in academic and business writing. Many are native speakers and able to perform any task for which you need help.

Tutorpro

Free Revisions

If you think we missed something, send your order for a free revision. You have 10 days to submit the order for review after you have received the final document.

Tutorpro

Timely Delivery

All papers are always delivered on time. In case we need more time to master your paper, we may contact you regarding the deadline extension.A 100% refund is guaranteed.

Tutorpro

100% Confidential

We use several writing tools checks to ensure that all documents you receive are free from plagiarism. Our editors carefully review all quotations in the text.

Tutorpro

24/7 Customer Services

Tutorpro support agents are available 24 hours a day 7 days a week and committed to providing you with the best customer experience. Get in touch whenever you need any assistance.

Try it now!

Calculate the price of your order

Total price:
$0.00

How it works?

Follow these simple steps to get your paper done

Place your order

Fill in the order form and provide all details of your assignment.

Proceed with the payment

Choose the payment system that suits you most.

Receive the final file

Once your paper is ready, we will email it to you.

Tutorpro Homework Help Services

At Tutorpro, we have top rated masters and PhD writers who will help you tacke that homework and score A+ grade. Tutorpro services covers all levels of education : high school, college, university undergraduate, masters and PhD academic level.

Essays

Essay Writing

No matter what kind of academic paper you need and how urgent you need it, you are welcome to choose your academic level and the type of your paper at an affordable price. We take care of all your paper needs and give a 24/7 customer care support system.

Tutorpro

Admissions

Admission Essays

An admission essay is an essay or other written statement by a candidate, often a potential student enrolling in a college, university, or graduate school. You can be rest assurred that through our service we will write the best admission essay for you.

Tutorpro

Editing

Essay Editing

Tutorpro academic writers and editors make the necessary changes to your paper so that it is polished. We also format your document by correctly quoting the sources and creating reference lists in the formats APA, Harvard, MLA, Chicago / Turabian.

Tutorpro

Revision

Revision Support

If you think your paper could be improved, you can request a review. In this case, your paper will be checked by the writer or assigned to an editor. This is free because we want you to be completely satisfied with the service offered.